We’ve already posted about Blackhill Quarry restoration and how Aggregate Industries’ signs that adorn the area warn that:
These works will involve large mobile plant being active on site for around 12 months from September / October 2017. Throughout these operations no material will be imported into the site, processed on site or taken off site.
But what AI says is often different to what AI does, and finished material is certainly being "taken off site" - as it should, if it’s not to be wasted - and sold into locations elsewhere in Devon.

In fact, HGVs have been streaming out of Blackhill Quarry in an obvious push to clear the stocking area before the end of this year - when both this area and the plant area are due to be restored.


That timetable was formalised back in 2013, but even with four years’ notice the company will struggle to meet these deadlines; the plant still shows no signs of coming down.