Sunday, 16 July 2023

Aggregate Industries’ Straitgate update for June

Aggregate Industries has provided the following update for the work the company carried out in June, in relation to its permission to quarry Straitgate Farm: 
In June the decision was taken to write a third time to owners of private water supplies who had not yet signed up to the monitoring scheme to give them a further chance to be part of the scheme. People who have already signed up were contacted to advise that visits to be undertaken as part of the preparation of the monitoring scheme would take place in the Autumn and that we would be in touch nearer the time. 

Other works related to the permission for the importation of material into Hillhead Quarry were that the widening of Clay Lane was completed and this is now open to two way traffic.