Wednesday, 5 June 2024

Aggregate Industries’ Straitgate update for April & May

Aggregate Industries provided the following update this week in relation to implementing its permission to quarry Straitgate Farm:  
The May update would be that we have now submitted the first batch of schemes required by condition (of which you have copies) to Devon for formal approval.  During June I also hope to be in a position to submit our water monitoring scheme and the written scheme of [archeological] investigation.
For April, the company provided this update: 
Please find attached copies of the schemes that I have submitted to Devon [County Council] today. 
The schemes referred to by Aggregate Industries include: 
Condition 7 (Landscape and Ecological Management Plan) 
Condition 20 (Travel Plan) 
Condition 22 (HVO Use) 
Condition 26 (Airport Safeguarding) 
Condition 33 (Dust and Air Quality) 
Condition 42 (Hedgerow along A30)